Updates

Glen Cove Remedial Progress

Update, week ending May 13, 2011

photo 1
Loading excavated soil for disposal

Work on the former Manufactured Gas Plant site at the LIPA substation in Glen Cove commenced on February 28, 2011.  The first work included the mobilization of equipment and other items necessary to execute the scope of work.  Work this week included continuing the excavation, transportation and disposal of impacted soils within the slide rail shoring in grid boxes 1 through 8.  Excavation areas were then backfilled with clean fill to within 5’ of finish grade. The crane used for construction of the retaining wall was demobilized. It is expected that with the wall construction, followed by the remedial excavation, the total project will take approximately 120 days to complete.

photo 1
Excavation area showing grid boxes

For the week beginning May 16, remedial activities will include continuing the excavation, transportation and disposal of impacted soils within the slide rail shoring in grid boxes 9 through 14.  Excavation areas will continue to be backfilled with clean fill up to within 5’ of finish grade.  Work will also include continuing the operation of the WWTP and demobilization of select equipment.  Deliveries will continue coming to and going from the site.   Work will be conducted Monday-Friday from 7:00 AM until 6:00 PM and Saturdays from 8:00 AM until 6:00 PM.  Saturday work is necessary to complete the project before the substation’s peak demand season.

photo 1
Cleaning truck tires before departure

As a reminder, National Grid has received approval from The City of Glen Cove that authorizes a 24 hour parking ban Monday through Saturday for approximately 50 feet on each side of the entry to the site at the corners of Grove and Stanco Streets.  This ban provides adequate space for trucks entering and leaving the Site. Truck traffic will enter and exit onto Grove Street towards Cedar Swamp Road. No Parking signs have been posted and the ban will be enforced by the Glen Cove police. The ban will be in place Monday – Saturday, 24 hours a day, for the duration of the project. Flyers outlining the parking changes have been distributed in the neighborhood.

photo 1
Odor and dust suppressing foam on excavated material

A fact sheet summarizing the project and its potential impacts to the residents has been sent to nearby residents summarizing the work. The Fact Sheet, the finalized Phase I Remedial Action Work Plan and information about the parking ban can also be found in the Key Documents/Major Reports section of this website. A link to the Fact Sheet and Parking information can be found below. The Fact Sheet and Handout are also available at the Site.

National Grid previously awarded the remediation of the Glen Cove former Manufactured Gas Plant site to Posillico Environmental, Inc. of Farmingdale, New York (Posillico).  Posillico will be completing the excavation portion of the overall site remedy as described in the New York State Department of Environmental Conservation approved Remedial Action Plan.  National Grid has retained AECOM to provide Construction Management services during the remedial action.  GEI will be the Design Engineers of record, act as Environmental Consultants for the remedial execution phase and perform site wide air monitoring.  

As work proceeds, the web site will be updated periodically to ensure the community is informed of the project schedule and progress.

 

Glen Cove Phase 1 Remediation Fact Sheet.pdf

Glen Cove Parking Ban Handout - English.pdf

Glen Cove Parking Ban Handout - Spanish.pdf